Walkability along Weaver Drive is about to take a major step forward. Starting Monday, November 9th, construction will officially begin on a new sidewalk stretch connecting key local spots, businesses, and health services in Granville. The new pathway will run along Weaver Drive, connecting StoryPoint Granville past Snapshots Lounge, Licking Memorial Family Practice, and Sandra’s Hair Salon, Park straight through to North Main Street.
Timeline, Contractor & Traffic Impact
Contractor: Work is being completed by The Shelly Company out of Thornville, Ohio.
Timeline: Construction is expected to wrap up in about two weeks (weather dependent), with the goal of having everything completed before Thanksgiving.
Traffic & Access: Drivers should prepare for intermittent lane restrictions on Weaver Drive, though two-way traffic will be maintained using flaggers. The highest impact to traffic will occur during the initial tree removal phase starting Monday, November 9th. Please plan for minor delays when traveling through the area.
Funding & Community Impact
The project was officially awarded at a total contract bid of $108,000, funded primarily through funds generated by the Weaver Drive Tax Increment Financing (TIF) district, alongside a small portion of non-TIF funds.
Established in 2019 following the development of the Middleton complex (now StoryPoint) and the conversion of the former trailer park into The Cottages, the 10-year TIF (2020–2029) was designated to support public infrastructure like pathways, lighting, storm management, and water lines.
While the TIF’s first project reimbursed the critical water line extension completed up Weaver Drive in 2023, this sidewalk represents the first directly visible, public-facing benefit funded by the TIF.
Looking Ahead
The primary goal of the new sidewalk is to create a safe, accessible pedestrian connector to South Main Street. As our local corridors grow, projects like this lay the groundwork for future community connections—including long-term possibilities for greater pedestrian access.
Keep an eye out for project signs going up near the pathway area as construction gets underway next week. We look forward to seeing residents enjoy this safe new connection!